Project Information
Grandview park Renewal
Project Type: Park Renewal
Project Status:Construction
Expected Completion: Summer 2011
Park Details: Grandview Park
Key Dates:
June 3, 2009 - Public open house
October 3, 2009 - Public open house.
January 19, 2010 - Concept design review
February 2010 - Concept taken to Board for discussion/ approval
Park under construction July 2010 through August 2011
May 14, 2011 - Multi-use Court Opening
August 5th -Playground opening
Contact:
David Yurkovich, Landscape Designer
604-257-6932
Ernest Fanthorpe, Project Manager, Field House
604-257-8458
Project Description
The Cenotaph Plaza, new washrooms, playground and multi-use sports court are now open.
Portions of Grandview Park remain closed for construction. Revised anticipated opening dates are:
August 26th - north west corner and large open southern grass area-
Community Participation
June 3, 2009 - Public open house
October 3, 2009 - Public open house
January 19, 2010 - Concept design review
February, 1 2010 - Board meeting - Concept approval. Concept "B" was approved by the Board. (See sidebar illustration)
Panels for January 19 Open House
Fieldhouse Drawings
Reports and Links
January 21, 2010 Staff Report recommending Approval of Concept and Consultancy Award -
Grandview Park Upgrade 