Urban Design Panel
Minutes
For: Wednesday, January 23, 2002
Index
Present
1133 Seymour Street
400 Beach Crescent
822 Seymour Street
Present: Members of the Urban Design Panel:
Tom Bunting, Chair
Walter Francl, Deputy Chair (Items 2 and 3)
Lance Berelowitz (Items 1 and 2)
Jeffrey Corbett
Gerry Eckford
Alan Endall
Bruce Hemstock
Richard Henry
Jack Lutsky
Maurice Pez
Regrets:
Joseph Hruda
Sorin Tatomir
Recording Secretary:
Vivian Guthrie, Raincoast Ventures
1. Address: 1133 Seymour Street
DA: 405395
Use: Mixed Retail/Residential (22 & 33 storeys)
Zoning: DD
Architect: Hewitt & Kwasnicky
Owner: Amacon-Omni Management
Review: Second
Staff: Ralph Segal/Anita Molaro
EVALUATION: SUPPORT (8-0)
Introduction
Chair Bunting advised that a response to the prior to' letter
had been distributed on the table.
Ralph Segal, Development Planner, introduced the application noting
that it had been previously viewed by the Panel and had been approved
in principal by the Development Permit Board with conditions. He noted
that the application brought new life to the area that could lead to improvements
for the downtown Granville corridor. Referencing the project model, Mr.
Segal led the panel in a detailed review of the project in the context
of the surrounding area.
Previous Panel concerns were reviewed and it was noted that the bulk
of both towers has been reduced while the height of the second tower has
increased to maintain floor space. Mr. Segal noted that separation of
the towers had improved, as had the design of the podium element to become
more of a statement. He noted that in addition to providing an additional
townhouse the design had created office space at ground level connected
to the residential above.
Mr. Segal requested the Panel's comments regarding:
porte-cochere elements and loading areas;
3-D resolution and evolution of the tower geometry;
separation at the base of the assemblage at plaza level between
podium and tower;
overall expression of the podium;
break in the street tree planting to announce entrance of the film
centre;
treatment of the street corner at Seymour and Davie; and
quality of the public realm interface on ground level especially
with respect to the relationship between the plaza and park.
In response to questions, Mr. Segal provided information on the downtown
vision and the establishment of the greening of the streets, felt to be
paramount to public realm, by virtue of the double row of trees. He advised
the park design had received public input and advised that the Vancouver
Park Board had established programmatic ideas regarding active and passive
areas of the park. He advised that the podium façade supports a
large screen to be used for projection purposes for announcements, cultural
events, etc., and that the trees would block views of the screen from
the park.
Applicant's Opening Comments: Donato Decotiis and David
M. Hewitt joined the Panel for consideration of this Item.
Mr. Hewitt discussed the means by which the Panel's previously raised
concerns had been addressed and commented regarding changes made to the
project, including:
book end framing of project by entrances;
pipe railings link different uses;
two porte-cocheres providing retail loading docks and public access
to the film centre;
reduction in light pollution' to direct light out to park
and not focus on adjacent residential buildings;
private open spaces café area between film centre and residential
component;
checkerboard pattern on plaza mimics Hollywood squares;
4th floor blocks out overview, and allows public weather protection;
retail component on Davie has been reduced to 25 foot elements;
and.
sweeping curve of the film centre provides a dramatic approach.
In response to questions from the Panel, the applicants provided additional
information regarding the influence of geometric elements, with the film
centre being key and other elements providing counter point and stepping-off'
energy. It was noted that the corner element of the towers related to
views and the sun, and that the plaza's hard surface would be comprised
of different textures and colour with a concrete and sparkle characteristic
to add to the film star' ambience. The Panel was informed that,
at the corner of Davie and Seymour, the designers proposed a similar pattern
linking the hard surface areas, but without imposing a character on the
retail stores.
The Panel reviewed the model and posted materials.
Panel's Comments
Panel members strongly endorsed the public animated edge of the building
projection screen with the park and public realm in general. Most felt
that it would be preferable to encourage public views to the screen from
the park while understanding staff's reservations regarding the double
tree planting without a commitment on behalf of the applicant to provide
the screen. A few members suggested that it might be better to plant the
trees and consider removing them once the screen was in place. In general,
the Panel was in favour of some rearrangement/removal of the trees for
this particular opportunity to have the project's screen more visible.
Staff and the applicants were urged to engage the Vancouver Park Board
in full discussion of this public benefit opportunity.
Several members suggested a refinement of the portal' element
at the retail level at the lane. Another member felt that the curve along
Davie invited public use of the park. In discussion of the ground plane
materials, the applicants were encouraged to use simple materials to achieve
a bold, sophisticated manner.
Members commented that the semi-private open space had improved but
that this area and the roof top design was challenged by scale and exposure
issues. A suggestion was to carry the film theme throughout. A more intense
program with more programmed space was also suggested.
The application was commended for the very creative loading resolution
and dual use of the area.
In general, the Panel considered the application to be a handsome, vital
project that would bring an exciting cultural dynamic to the area. There
was some support for the revised geometry of the towers, but several members
felt that the design of the towers could be simplified to achieve a slimmer
profile and that a simplification of the tower form was needed in general,
as it was still too fractured and overly complex, especially for the taller
tower. Several members felt the base of tower 1 (taller tower) was still
unresolved or not strong enough to match the strength of the tower. Some
more detailed attention is needed at the Seymour public realm. It has
improved, but was not felt to be up to the strength of the rest of the
project. One member commented that the tower design was energetic and
powerful.
Applicant's Response
Mr. Hewitt expressed appreciation for the Panel's comments and suggestions.
He noted how the building design had incorporated the portal element to
hide the service area of a neighbouring building and how the complexity
of the towers reflected a design preference to treat balconies as an extension
of the form as well as an opportunity to step back massing elements. The
applicant looked forward to a dialogue with the Vancouver Park Board.
***
MOTION
It was moved by Mr. Berelowitz and seconded:
That the Urban Design Panel recommend to City Council and the Director
of Planning that the Vancouver Park Board be encouraged to enter into
a dialogue with the applicant for 1133 Seymour Street to develop the potential
interface of the film centre with the future design of the park across
the street. It is also recommended that the dialogue not be a condition
of the application's approval.
- CARRIED
MOTION
It was moved by Mr. Eckford and seconded:
That the Urban Design Panel recommend to City Council and the Director
of Planning that the Vancouver Park Board be requested to present plans
for proposed new and redesigned parks in the urban centre to the Urban
Design Panel for its review and comment.
- CARRIED
2. Address: 400 Beach Crescent
DA: 406387
Use: Residential (18 & 24 storeys)
Zoning: CD-1
Architect: James Cheng
Owner: Concord Pacific Group
Review: First
Staff: Jonathan Barrett
EVALUATION: NON-SUPPORT (2-7)
Introduction
Jonathan Barrett, Planning, referenced the model and discussed the
context of the complete development application with other projects under
construction in the area. The application is comprised of two towers (24
and 18 storeys), with 8, 5 and 4 storey flats and townhouses. Located
beside George Wainborn Park, the site also has the benefit of facing the
waterfront. It was noted that the application does not meet some of the
guidelines for the Beach neighbourhood and requests a density transfer
of approx. 20,000 sq. ft. from the larger neighbourhood of which it is
a part.
The Panel's comments were sought with respect to the Beach Neighbourhood
Guidelines, as follows:
the scale of a continuous low-rise along the waterfront;
Beach street elevation 6-storey streetscape;
gaps in the perimeter of the development;
tower floor plate size creating shadow onto park and narrowing
view corridors;
up to 8-storeys facing the park;
access to grade level units from public realm (Stanley Park);
one point for access to parking and drop off; and
added density on site.
Applicant's Opening Comments
Carl MacDonald, Terry Mott, Chris Phillips and Fred Roman joined
the Panel for consideration of this Item.
Mr. Mott explained in detail the design rationale of the project and
the attempt to meet the guidelines for the area. He specifically addressed
the desirability of public access slots' into the secret'
garden and the use of water in the landscaping for ambience as well as
security. An attempt had been made to lower the scale of the project at
the corners and some buildings had exceeded the number of stories to address
site slope and scale issues. He also discussed the primary access for
visitors and the difficulties in providing direct access to the park and
foreshore walk. Mr. Mott demonstrated by use of diagrams that shadowing
by the tower elements is an issue in the morning but quickly moves out
of the park towards noon. Also noted were difficulties with circulation
in residential units and accessibility to different levels.
Mr. Mott commented on the disposition of massing and the livability
of suites obtained by orientation. He noted that vehicular access allows
pedestrian and cyclist transitions, and that two access points have been
provided for fire trucks.
The Panel reviewed the illustrated guidelines, model and posted materials.
Panel's Comments
The Panel acknowledge the difficulties of the site; the onerous prescriptions
of the guidelines and bylaw but admitted discomfort with considering the
project as a full development permit application.
In general the Panel considered the breaks in the perimeter to enhance
the public experience and applauded the use of water in the landscape.
One member queried the relative size of the waterways to the buildings
and whether more private open space would be desirable. While security
was a consideration, it was felt that access to the park and seawall at
grade was a missed opportunity. Panel members suggested that a more direct
access for pedestrians would be beneficial, as would a safer design of
the cycle and pedestrian path to the waterfront walk.
There was no opposition to the low-rise buildings proposed for the perimeter
of the site. Several members commented that the towers and flats would
be less foreign to the neighbourhood if provided with a shoulder'
or a wider base towards ground level. Members commented that a more pleasant
relationship could be achieved between the building mass and the foreshore
park.
It was noted that the dog leg' design and elevator core blocked
views and sun, compromising the livability of some interior suites. Further,
it was suggested that the southeast corner townhouses seemed underdeveloped
(stripped down), and that the connection to the tower from 8 storey was
not architecturally convincing.
The Panel considered the syncopation and modulation of the massing somewhat
successful, but were not convinced that the project could support the
extra density successfully. Some felt that the width of the floor plate
spread too far on the city side and infringed on the views of the towers
behind. The Panel gave some consideration to market demands as well as
to the established guidelines for the neighbourhood. Some members suggested
the design could be more complimentary to neighbouring projects that conformed
to the guidelines. One member suggested this was a site that could challenge
the guidelines.
The application was commended for its well-executed architectural scheme,
detailing and thoroughness of presentation. It was generally thought that
breaking up the massing with the view corridors and water feature enhanced
the project and the modulation of low-rise to hi-rise worked well. However,
it was recognized that fundamental levels of urban design had not been
addressed, and that some of the particular massing did not relate well
to other developments.
Applicant's Response
The applicant expressed appreciation for the Panel's thorough evaluation.
3. Address: 822 Seymour Street
DA: 406340
Use: Mixed
Zoning: DD
Architect: W. T. Leung
Owner: D.T.K.H. Robson Dev. Ltd.
Review: First
Staff: Anita Molaro
EVALUATION: SUPPORT (8-0)
Introduction
Anita Molaro, Planning, referencing the project model, introduced
the proposal for 822 Seymour Street in the context of the surrounding
area. She advised that the project is for a mixed-use commercial and residential
development consisting of underground parking, retail on ground and second
floors, offices on the third floor and 85 units of residential rental
apartments on the upper floors. Although not required to, the project
meets setback offsets as prescribed in Downtown South guidelines and is
massed to achieve a slim tower to the west side of the site, minimizing
shadowing impact. Ms. Molaro further noted the high quality in architectural
form empathetic to the pedestrian environment and skyscape.
The Panel's comments were sought with respect to the application's overall
massing, shadow impacts on Robson Street, quality of finish elements,
and the adequacy of residential greenspace.
In answer to questions from the Panel Ms. Molaro advised that there
was no application of any relaxations, the residential urban space was
not prescribed in the downtown area, and that the commercial and office
level had substantial greenspace while such space was minimal in the residential
component.
Applicant's Opening Comments
Jane Durante, Barry Krause, Wing Ting Leung, and Darren Swift joined
the Panel for consideration of this Item.
Mr. Leung referencing the design rationale noted that the underlying
idea of the design was to sustain a vibrant extension of Robson Street
while integrating a simple form with sculptured visual clues to the residential
tower (e.g. balconies) with other buildings in the Downtown Core. The
residential entrance off Seymour is accessed through green landscaped
terraces, creating a green visual space. While not an active open space,
the concept suggests an experience of walking through landscaping.
Ms. Durante discussed the project's landscape design and commented on
the additional greening.
The Panel reviewed the model and posted materials.
Panel's Comments
The Panel expressed its enthusiastic support for the project and
commented that while current elevations of the retail space were considered
elegantly appropriate, further detail to the street level would enhance
the unique flavour of Robson Street. Likewise, the streetscape along Seymour
could use a richer level of detail. The Panel suggested that further consideration
be given to the plaza area at Robson and Seymour.
The greenspace allotted to the residential area was deemed sufficient
given the location of the site. The Panel commented on the successful
treatment of the entry sequence, and noted that careful consideration
should be given to the type of plants in the residential entry given the
possibility of shadowing by future buildings.
Members commented on the effective massing of the project that complimented
larger commercial buildings in the area and noted that the architect had
used the best orientation of the tower to preserve views. Suggested improvements
were offered related to the detailing of the blank concrete wall on the
lane elevation as viewed by pedestrian and vehicular traffic travelling
north. The overall quality of materials was considered to be very good.
Applicant's Response
Mr. Leung thanked the Panel for its comments and advised that in
his consideration design continues past the development permit stage and
assured the Panel that the project would evolve to enhance and compliment
Robson Street complexities.
|