We are continuing to monitor the Portland Loos.

Timeline

Here is our progress and planned steps.

  • Fall 2021

    Demolition of the fieldhouse

  • Spring 2022

    Installation of the Portland Loos and new drinking fountain

  • Summer 2022

    Installation complete

    • Monitoring underway