We’re planning to renew the playground at David Lam Park.
Park Board funding for the project will be supplemented by a financial contribution from the Elsie Roy Elementary Parent Advisory Committee, which will be generated through upcoming fundraising efforts.
We look forward to hearing your ideas regarding this exciting project.
What's happening
Concept designs will be developed and brought to the community for input at an open house later this year.
If you would like to be added to the stakeholders list or have any questions about this renewal, contact the project manager below.
Timeline
Here is our progress and planned steps.
-
Spring/summer 2019
Meet with stakeholders and develop initial concept designs
-
Fall 2019
Community open house
-
Fall 2019/winter 2020
Develop revised design based on feedback
-
Spring 2020
Project tendered for construction*
-
Spring 2020
Board approval of construction contract*
-
Summer 2020
Playground is closed for construction*
-
Summer/fall 2020
Renewed playground is open
*Subject to funding.
Contact us
David Yurkovich
Project Manager
david.yurkovich@vancouver.ca
604-257-6932