The Vancouver Park Board is upgrading the grass field at Montgomery Park to increase field capacity by up to 50% and ensure year round usage.
The design of the fields was completed through consultation with the Vancouver Field Sports Federation.
Upgrades include:
- Expanding playfield areas
- Installing new turf grass
- Irrigation
- Drainage
- Fences
- Goal posts as required
What's happening
Project update
COVID-19 has resulted in significant disruptions to supply chains worldwide, causing a shortage of materials, including pipes used for irrigation and drainage. Despite these challenges, the project is on track for completion by end of April 2022.
Important note Upon completion, we will continue to keep the fields closed to the public for a few months to allow the turf grass to fully establish. Depending on the development of the turf, the soccer fields should be usable early July of 2022.
Open house
Thank you for attending our open house to explore the improved designs on September 21, 2019.
Timeline
Here is our progress and planned steps.
-
May - Sept 2018
Concept design
-
April - Oct 2019
Detailed design
-
Sept 21, 2019
Open house
-
Dec 2019
Tender process
-
Aug 2020
Construction begins
-
We are here
-
April 2022
Construction completion
-
June 2022
Grass establishment
-
July 2022
Field open
Contact us
Sardar Muntasir
Project Manager
sardar.muntasir@vancouver.ca