The Vancouver Park Board is upgrading the existing grass fields located at Slocan Park.
The intent of the field renewal program is to upgrade all 3 grass fields to ‘A’ level fields, increasing playing capacity by as much as 50%.
The design of the fields was completed through consultation with the Vancouver Field Sports Federation (VFSF) External website, opens in new tab and the local community. Upgrades include:
- Regrading and expanding play areas
- Installing new irrigation and drainage systems
- New goal posts and ball control fences at the ends of the fields
The Park Board has finalized the design for the upgrades. Construction is targeted to start July 2019 and substantially completed by December 2019.
Fields will remain closed until May 2020 to allow the grass to fully establish.
What's happening
On June 8, 2019, we held an open house about the project at Slocan Park.
View the open house information displays PDF file (3 MB)
The project will be presented to the Park Board on June 24, 2019.
Timeline
Here is our progress and planned steps.
-
May - Sept 2018
Concept design development
-
January - April 2019
Detailed design
-
June 8, 2019
Open house
-
June 24, 2019
Park Board approval
-
July - Dec 2019
Construction
-
We are here
-
May 2020
Field opens
Contact us
Sardar Muntasir
Project Manager