Intersection on Oak Street

Oak Street water main upgrades

We’re upgrading critical water infrastructure along Oak St from 64th Ave to 71st Ave.

What's happening

Work completed July 2020

Crews replaced 720 metres of existing water main. Work was required to replace an aging water main, support approved redevelopment in the area, and increase fire protection coverage. 

The work included repairing the road damaged as a result of the water main construction and sidewalk restoration where required.


Details

Location

Duration

May 11 to late July 2020

  • Installation of east/west pipes: Oak St between 64th Ave and 70th Ave
    May 11 to 25
  • Full water main construction: east side of Oak St
    May 25 to late July

Work hours

Monday to Friday: 7:30am to 5pm, extended as needed

Weekends: as needed


How this project may affect you

Contact us

Do Nguyen
Community Liaison
604-673-8458
oakwatermain@vancouver.ca