Project Information

Brockton Point Lighthouse Structure Restoration

Project Type: Park Improvements / Upgrades
Project Status: Construction
Project Start: September 13, 2010
Expected Completion: February 21, 2011

Park Details: Stanley Park

Contact:
Sam Bachra, Project Manager
604-257-8604

Project Description

The Vancouver Board of Parks and Recreation is restoring the concrete structure at Brockton Point in Stanley Park.

The work includes structural repairs to the existing retaining walls, stairs and observation decks.
This $1.5 million project is funded in part with a $750 thousand Government of Canada Federal Infrastructure Stimulus Fund grant.

Pedestrians will be rerouted from the seawall to the upper bike path between the Totem Poles and Lumberman's Arch. The bike path will be a shared path during this time period.