Charleson Park playground

Charleson Park playground upgrade

The Vancouver Park Board is replacing a portion of the playground at Charleson Park.

The small playground adjacent to False Creek Elementary School, the tower, and the swings need to be replaced due to their age and condition. The lower playground adjacent to the swings was replaced in 2013 and will remain.

What's happening

Final concept

Construction is currently underway and anticipated to continue until fall/winter 2020.

Thank you for joining us

In December 2018, we held an open house at False Creek Elementary School to share ideas and gather feedback on the preliminary concept and equipment options. This feedback was used to revise the concept design and begin detailed design of the new playground.

Timeline

Here is our progress and planned steps.

  • December 2018

    Public open house

  • Winter/
    spring 2019

    Detailed design

  • Spring 2020

    Construction begins

  • We are here
  • Fall/
    winter 2020

    Playground renewal complete

Contact us

Jason McMillen
Project Coordinator
jason.mcmillen@vancouver.ca