We're upgrading the gravel all-weather field in Beaconsfield Park to a synthetic turf field based on recommendations in the city-wide Sport Field Strategy PDF file (9.1 MB) and direction provided by Park Board PDF file (185 KB) and Council PDF file (57 KB) motions in 2025.
Benefits to the field upgrade
The upgraded field will:
- Increase capacity to help meet the rising demand for year-round, high-quality playing surfaces
- Provide equitable access to synthetic turf fields and promote participation in physical activity
- Use infill materials free from toxic contaminants
- Include infrastructure to manage environmental impacts, such as containment trays, raised curbs, and fencing screens to control infill migration
Proposed field upgrades
- Synthetic turf playing field with a playable surface measuring 100 metres long by 60 metres wide
- High-mast LED sport field lighting with fixture shielding to control light spill and glare
- Player benches
- Circulation pathways
- Infrastructure to manage environmental impacts
Concept design approved and field width confirmed
On March 30, 2026, the Park Board approved the project concept design on the condition that the synthetic turf field have a minimum playable width of 60 metres.
Further investigation has confirmed that a 60 metre wide synthetic turf field is feasible.
Park Board reports and design documents
Field upgrades timeline
-
2009
Shortlisted as potential turf field site
-
2018
Initial technical review and engagement
-
2024
Citywide Sport Field Strategy approved
-
2025
Board and Council motions
-
Fall 2025
Site analysis, feasibility, and environmental study
-
Spring 2026
Concept plan approval with amendment
-
Fall 2026
Amended concept plan
-
We are here
-
2027
Detailed design
-
2028
Tendering and approvals
-
2028
Target construction start
Contact us