Anderson Street upgrades

Road closures on April 9, 13, 15 and 16

Crews will be conducting water main work at the intersection of W 2nd Ave and Anderson St on:

  • Friday, April 9
  • Tuesday, April 13
  • Thursday, April 15
  • Friday, April 16

This work will require a full closure of W 2nd Ave between Anderson St and the laneway adjacent to Anderson St on the west side. One lane in each direction on Anderson St will be maintained. Access to and from Granville Island will be retained via Anderson St.

Some bus detours may be in effect. Visit translink.ca/alerts for more information.

We’re upgrading critical water and sewer infrastructure along Anderson St and W 2nd Ave.

Work includes the replacement of an aging water main and sanitary force main. The new water and sewer infrastructure will have a life expectancy of 100 years to help serve this growing neighbourhood.

What's happeningConstruction is underway

Transit stops #52061 and #58661 are temporary relocated until construction is complete.

See project map below for temporary stop locations.


Details

Location

Work will be underway on Anderson St under the Granville Bridge from W 2nd Ave to Island Park Walk and W 2nd Ave from Anderson St to Mariners Way.

Duration

  • Winter 2021 to summer 2021

Work hours

Monday to Friday: 7am to 5pm, extended hours as needed

Weekends: as needed


How this project may affect you

Related projects

Greenest City Action Plan

Greenest City is a bold initiative that addresses Vancouver's environmental challenges.

Transportation 2040 Plan

Our plan provides a vision for how people and goods move in and around Vancouver for the next 30 years.