Drake Street upgrades

We’re carrying out transportation upgrades to Drake Street between Burrard Street to Pacific Boulevard. This includes:

  • A 2-way protected bike lane between Burrard Street and Hamilton Street, with 1-way eastbound vehicle traffic only
  • A 1-way eastbound protected bike lane between Hamilton Street and Pacific Boulevard, with 2-way vehicle traffic retained

These upgrades will provide a more comfortable and convenient route for people walking and cycling through downtown and on the upgraded cycle and pedestrian routes on the Granville Bridge. 

This new design includes feedback we heard through engagement with community members, businesses, and stakeholders.

Review detailed plans for Drake Street improvements (1.8 MB)

What's happeningSummer 2025: Phase 3 construction underway

In July 2025, we’ll start the third and final phase of upgrades on Drake Street.

Work will take place at the Burrard Street intersection and between Granville Street and Pacific Boulevard.

As work progresses, expect:

  • Rolling intersection closures
  • Detours
  • Parking restrictions

We’ll maintain access to businesses and residences.


Details

Location

Duration

Phase 3 construction will take place between summer 2025 and spring 2026. 

Construction has been scheduled in 3 phases:

  • Phase 1 – early works: Drake Street from Hornby Street to Howe Street (completed October 2022)
  • Phase 2 – coordinated with the Granville Connector: Drake Street from Hornby Street to Granville Street (currently underway until late spring 2025) 
  • Phase 3: Drake Street at Burrard Street and from Granville Street to Pacific Boulevard 

Work hours

Monday to Friday: 7am to 5pm, extended hours as needed

Weekends: as needed


How this project may affect you

Contact us

Community Liaison

Phone: 604-873-7307
Email: drakeupgrades@vancouver.ca

 


Related projects

Transportation 2040 Plan

Our plan provides a vision for how people and goods move in and around Vancouver for the next 30 years.

Granville Connector

We're building the first phase of the Granville Connector with the installation of new pedestrian and cyclist connections across the bridge.