We're upgrading the aging water pipes along West Pender Street between Burrard Street and Cardero Street.
This project includes installing and replacing over 1 kilometre of drinking water infrastructure, with new pipes designed to last 100 years.
What's happeningPhase 1: Construction underway
Phase 1 of construction on West Pender St between Burrard and Bute St is taking place May to November 2024.
If you are travelling in and around the area, plan ahead and expect delays.
Phase 2
Phase 2 of construction will begin between Bute and Cardero St from May to December 2025.
Information icon We will send notification letters, place new signage, and provide updates on project impacts closer to the start of Phase 2.
Details
Location
Water main work will take place along West Pender Street between Burrard and Cardero Street.
Duration
Water main construction is scheduled in 2 phases:
- May to November 2024
- May to December 2025
Work hours
Monday to Saturday: 7am to 5pm, extended hours as needed
Weekends: as needed
Information icon Work that is required within intersections will be generally completed over weekends.