Shaughnessy area sewer upgrades

We’re upgrading critical sewer infrastructure in the Shaughnessy area, between West 26th Avenue and West 29th Avenue.

The existing sewer system will be replaced with a separated and larger‑capacity system, with 1 pipe for rainwater runoff and another pipe for sewage. This new sewer main will have a life expectancy of 100 years to help serve this growing neighbourhood.

As part of this work, we'll also be completing some curb replacement and street repaving.

What's happeningConstruction progress update

All sewer installation work is complete. Crews will be prepping areas for paving, completing paving and restoration work, and tidying up the site.

Crews will return to complete some additional work along Osler St crossing West King Edward St in the coming months. We will share updates closer to construction starting. 

During construction, expect: 

  • Road and lane closures
  • Detours
  • Parking restrictions

Details

Location

Between West 26th Avenue and West 29th Avenue in Shaughnessy. 

Duration

  • Phase 1: September 2025 to December 2025
  • Phase 2: December 2025 to January 2026
  • Phase 3: January 2026 to September 2026

Work hours

Monday to Friday: 7am to 5pm, extended hours as needed

Weekends and evenings: as needed


How this project may affect you

Contact us

Community liaison
Email: [email protected] 

Contact information, partner agencies, and website policies

City of Vancouver virtual assistant
Tell us how you found your conversation today