We’re upgrading critical sewer infrastructure in the Shaughnessy area, between West 26th Avenue and West 29th Avenue.
The existing sewer system will be replaced with a separated and larger‑capacity system, with 1 pipe for rainwater runoff and another pipe for sewage. This new sewer main will have a life expectancy of 100 years to help serve this growing neighbourhood.
As part of this work, we'll also be completing some curb replacement and street repaving.
What's happeningConstruction progress update
All sewer installation work is complete. Crews will be prepping areas for paving, completing paving and restoration work, and tidying up the site.
Crews will return to complete some additional work along Osler St crossing West King Edward St in the coming months. We will share updates closer to construction starting.
During construction, expect:
- Road and lane closures
- Detours
- Parking restrictions
Details
Location
Between West 26th Avenue and West 29th Avenue in Shaughnessy.
Duration
- Phase 1: September 2025 to December 2025
- Phase 2: December 2025 to January 2026
- Phase 3: January 2026 to September 2026
Work hours
Monday to Friday: 7am to 5pm, extended hours as needed
Weekends and evenings: as needed
How this project may affect you
Contact us
Community liaison
Email: [email protected]
