Renfrew-Collingwood water main upgrades

We’re upgrading the aging water mains near Renfrew Community Park. 

The project includes installing and replacing approximately 1.4 kilometres of drinking water infrastructure with new pipes designed to last for 100 years, maintaining a reliable and sustainable water supply for the future.

What's happeningConstruction begins this fall

Construction will be completed in 3 phases between late-fall 2025 and summer 2026.


Details

Location

  • Phase 1: Begins November 2025, work on Nootka St between E 20th Ave to E 22nd Ave
  • Phase 2: Begins January 2026, work along E 22nd Ave, from Kaslo St to Rupert St
  • Phase 3: Begins June 2026, work on E 20th Ave, from Nootka St to Lillooet St

Schedules and order of construction are subject to change.