We’re carrying out transportation upgrades to Drake Street between Burrard Street to Pacific Boulevard. This includes:
- A 2-way protected bike lane between Burrard Street and Hamilton Street, with 1-way eastbound vehicle traffic only
- A 1-way eastbound protected bike lane between Hamilton Street and Pacific Boulevard, with 2-way vehicle traffic retained
These upgrades will provide a more comfortable and convenient route for people walking and cycling through downtown and on the upgraded cycle and pedestrian routes on the Granville Bridge.
This new design includes feedback we heard through engagement with community members, businesses, and stakeholders.
Review detailed plans for Drake Street improvements PDF file (1.8 MB)
What's happeningJuly 2026: Phase 3 construction update
In August 2025, we started the third and final phase of upgrades. Construction is anticipated to be complete by August 2026.
Information icon Upgrades between Seymour and Richards streets have been delayed because of nearby development activity. Crews will return within the next year to complete this final stage of work.
Details
Location
Duration
Phase 3 construction will take place between summer 2025 and spring 2026.
Construction has been scheduled in 3 phases:
- Phase 1 – early works: Drake Street from Hornby Street to Howe Street (completed October 2022)
- Phase 2 – coordinated with the Granville Connector: Drake Street from Hornby Street to Granville Street (currently underway until late spring 2025)
- Phase 3: Drake Street at Burrard Street and from Granville Street to Pacific Boulevard
Work hours
Monday to Friday: 7am to 5pm, extended hours as needed
Weekends: as needed