This project will result in 1 kilometre of new sewer pipes with a life expectancy of about 100 years.
Separating a sewer system
We are replacing aging combined sewer infrastructure along Oak Street, West 70th Avenue, and Fremlin Street with separated pipes.
The upgrade of the sewer system will:
- Accommodate population growth in the Cambie Corridor
- Effectively manage heavier rainfall expected with climate change
- Handle higher capacities of rainwater and sewage separately
- Help protect the water quality in the Fraser River
The project is primarily funded by developers through the Development Cost Levy, with additional funding from local development projects.
What's happeningMarch 2025: Final paving underway, expect delays
From March 15 to 30, crews will be completing final paving work along Oak St and W 70th Ave. Expect temporary lane closures, detours, and reduced speeds during this period, including:
March 15 and 16:
- Oak St at W 70th Ave intersection reduced to 1 lane each way
March 17 to 30:
- Oak St open with minimum one lane traffic at all times
- Eastbound W 70th Ave closed, between Osler St and Shaughnessy St, with a detour in place at Granville St
Thank you for your patience and understanding while we complete this final stage of the project.
December 2024: Sewer upgrades complete
Sewer upgrade work along Oak Street, West 70th Avenue, and Fremlin Street was completed in December 2024.
Details
Location
Sewer upgrades:
- Phase 1: Fremlin Street from SW Marine Drive to W 70th Avenue
- Phase 2: W 70th Avenue from Fremlin Street to Oak Street
- Phase 3: Oak Street from W 70th Avenue to W 64th Avenue
Duration
Infrastructure upgrades and road improvements are scheduled from September 2023 to spring 2025.
Work hours
Work on Oak Street between W 70th Avenue and W 64th Avenue will take place overnight on weekdays (8pm to 5am) and on weekends, as needed.
Work will take place overnight to prioritize workers’ safety, minimize traffic impacts, and expedite the work.
How this project may affect you
Timeline
Here are our planned next steps:
-
September 2023
Daytime construction on Fremlin St starts
-
February 2024
Daytime construction on W 70th Ave starts
-
Summer 2024
Nighttime construction on Oak St starts
-
Winter 2024/2025
Sewer construction is complete
-
Spring 2025
Final street restoration is complete